Project Funding
Lead Gift in Memory of Jack Martin | $10,000,000 | |
GIPS QCPUF Funds - Improve accessibility | $750,000 | |
GIPS Building Funds - Track Resurfacing, Architectural Fees, & Field Turf | $1,250,000 | |
Private funds to be raised with Your help through GIPS Foundation - Primary Project | $3,300,000 | |
Total Funding Primary Project | $15,300,000 | |
Private funds to be raised with Your help through GIPS Foundation - Expanded Project | $1,700,000 | |
Total Funding Primary + Expanded Project | $17,000,000 |
Project Budget
Primary Project | ||
New West Stadium with 2 story press box | $10,900,000 | |
Renovate East Stadium, stands & interior | $1,080,000 | |
Track Resurfacing | $80,000 | |
New Turf | $750,000 | |
Architecture Fees | $787,815 | |
Project Contingency | $1,281,000 | |
Fundraising and Donor Recognition Wall | $270,000 | |
Uncollectable Pledge Allowance | $151,185 | |
Total Primary Budget | $15,300,000 | |
Expanded Project if funds allow | ||
New Addition to East Stadium | $1,400,000 | |
Architecture Fees | $86,100 | |
Project Contingency | $140,000 | |
Uncollectable Pledge Allowance | $73,900 | |
Total Expanded Budget | $1,700,000 | |
Total Budget Primary + Expanded Project | $17,000,000 |